Steel cutting - LNG Bunker vessel

May 26, 2022

On March 15th at Nantong CIMC Sinopacific Offshore & Engineering yard, the construction process of the first of our group’ LNGBV officially initiated with the first steel cut for the hull. This important milestone was verified by RINA inspectors as shown in the attached pictures. On April 15th, the yard started the steel cut for the hull of our second LNGBV. The construction of these units is currently on schedule, and they are expected to be ready by October 2023 and January 2024, respectively.